Claims

JCP CONSULT will be at your disposal at any stage of the project, even the Claims Here we show you some of our work done:

Date

2023.

Location

SAUDI ARABIA.

Service

Claim Preparation: Backcharges recovery, Extension of Time, Indirect and Equipments extra cost, Productivity Loss in Direct Manpower.

Final Value of the Project

USD 16.106.252,02

i

Project Type

BUILDING – GAS PLANT

i

Project Description

BUILDING WORKS INCLUDING PROCUREMENT AND CONSTRUCTION IN SOUTH GHAWAR GAS SEPARATION PLANT & ASSOCIATED FACILITIES PROJECT

Project Scope

4.600 m2 of buildings Construction (SubEstation 230 KV, SubEstation 13.8 KV, Process Interface Building (PIB), Operation Support Facilities (OSF), Gate House.

Our Services

Forensic Schedule Analysis (Planned vs. As Built), Reponsabilities Analysis, Quantum of the asociate cost of the EoT and Productivity Loss because more than 100 Changes Orders Request.

Date

2022.

Location

SAUDI ARABIA.

Service

EXTENSION OF TIME REQUEST AND EQUITABLE ADJUSTMENT COSTS TO THE CONTRACT

Final Value of the Project

USD 16.596.454,66

i

Project Type

FENCING – GAS PLANT

i

Project Description

Fencing Works: Supply and Instalation of Safety Fence.

Project Scope

Fencing Works: Supply and Instalation of Safety Fence in three (3) different Areas and Seventeen (17) locations.

Our Services

Forensic Schedule Analysis. Evaluation of the Extension of Time (EoT), responsabilities ans aditional cost: Indirect Manpower and Equipments.

Date

2022.

Location

SAUDI ARABIA.

Service

Extension of Time Evaluation (Analysis Forensic of the Schedule), Quamtum of Additional Cost.

Final Value of the Project

USD 21.741.713,56

i

Project Type

TEMPORARY FACILITIES – GAS PLANT

i

Project Description

TEMPORARY FACILITIES CONSTRUCTION

Project Scope

Temporary Camp for 500 Persons, Temporary Offices and Site Warehouse.

Our Services

Forensic Schedule Analysis. Evaluation of the Extension of Time (EoT), responsabilities and Quantum: Indirect Manpower and Equipments and Productivity Loss in Direct Manpower.

Date

2009.

Location

SAUDI ARABIA.

Service

Major Impacts on Project Costs

Final Value of the Project

USD 480.000.000

i

Project Type

GAS PLANT

i

Project Description

Increase 851 MMSCFD in gas processing capacity

Project Scope

Gas inlet handling facilities, one Sour Water Stripper Unit, two DGA gas treating units, one Sulfur Recovery Unit with thermal oxidizer, one TEG/propane refrigeration system for gas Dehydration and Dewpoint Control, two Sales Gas Compressors, and the re-gearing of the four existing Sales Gas Compressors.

Our Services

Extension of Time analysis due to several Change Orders Request, Quantum of Indirect Personnel, Subcontractors.

Date

2002.

Location

VENEZUELA.

Service

Claim based on pending Aditional Works

Final Value of the Project

USD 3.000.000

i

Project Type

GAS COMPRESSOR PLAN.

i

Project Description

Electrical and Instrumentation Works

Project Scope

Electrical and Instrumentation Works

Our Services

Extension of Time due to Material Delay Delivery, and Quantum for Manpower and Equipments additional Costs.

Date

2001.

Location

VENEZUELA.

Service

Extension of Time due to Material Delay Delivery, and Quantum for Manpower and Equipments additional Costs.

Final Value of the Project

USD 600.000

i

Project Type

Small Bore Piping Installation

i

Project Description

Installation of 6.000 LM of Small Bore Pipe, includind Pipe Support prefabrication and insallation.

Project Scope

Pipe for Services: Water, Air, Vapor and Nitrogen. Cooling Water Systems, Fire Water Systems and Drinking Water.

Our Services

Extension of Time due to Material Delay Delivery, and Quantum for Manpower and Equipments additional Costs.

Date

1999

Location

VENEZUELA.

Service

Extension of Time due to Material Delay Delivery, and Quantum for Manpower and Equipments additional Costs.

Final Value of the Project

USD 3.200.000

i

Project Type

CIVIL WORKS – GAS PLANT

i

Project Description

Erection Precast Concrete Pipe Rack.

Project Scope

Erection Precast Concrete Pipe Rack. 358 Columns and 991 Beams, with a total Weigth: 7,791 Tons.

Our Services

Extension of Time due to delays in the delivery of Materials, calculation of the Impacts on the cost of Direct and Indirect Personnel, and Equipment.

Date

1998

Location

VENEZUELA.

Service

CLAIM PENDING ADDITONAL WORKS

Final Value of the Project

USD 13.200.000

i

Project Type

GAS COMPRESSOR PLANT

i

Project Description

Erection of two (2) Gas TurboCompressors

Project Scope

Erection of two (2) Gas TurboCompressors, KOD and Flare, including all the Pipe Prefabrication and Intalations, Electricity and Instrumentation Works.

Our Services

Support and negotiate several Change Orders pending.

Date

1992.

Location

VENEZUELA.

Service

Negotiate additional works, quantities increase, and over cost.

Final Value of the Project

USD 7.000.000

i

Project Type

GAS COMPRESSOR PLANT

i

Project Description

Erection of three (3) Gas Compressors Miniplants

Project Scope

Erection of three (3) Gas Compressors Miniplants with Electrical Motor of 10.000 HP, including Modular Control and Power Room. Prefabrication and instalation of Pipe. Electrical and Instrumentation works

Our Services

Contract close, including additional work, quantities increase, and claim for overcosts.