Claims
JCP CONSULT will be at your disposal at any stage of the project, even the Claims Here we show you some of our work done:
Date
2023.
Location
SAUDI ARABIA.
Service
Claim Preparation: Backcharges recovery, Extension of Time, Indirect and Equipments extra cost, Productivity Loss in Direct Manpower.
Final Value of the Project
USD 16.106.252,02
Project Type
BUILDING – GAS PLANT
Project Description
BUILDING WORKS INCLUDING PROCUREMENT AND CONSTRUCTION IN SOUTH GHAWAR GAS SEPARATION PLANT & ASSOCIATED FACILITIES PROJECT
Project Scope
4.600 m2 of buildings Construction (SubEstation 230 KV, SubEstation 13.8 KV, Process Interface Building (PIB), Operation Support Facilities (OSF), Gate House.
Our Services
Forensic Schedule Analysis (Planned vs. As Built), Reponsabilities Analysis, Quantum of the asociate cost of the EoT and Productivity Loss because more than 100 Changes Orders Request.
Date
2022.
Location
SAUDI ARABIA.
Service
EXTENSION OF TIME REQUEST AND EQUITABLE ADJUSTMENT COSTS TO THE CONTRACT
Final Value of the Project
USD 16.596.454,66
Project Type
FENCING – GAS PLANT
Project Description
Fencing Works: Supply and Instalation of Safety Fence.
Project Scope
Fencing Works: Supply and Instalation of Safety Fence in three (3) different Areas and Seventeen (17) locations.
Our Services
Forensic Schedule Analysis. Evaluation of the Extension of Time (EoT), responsabilities ans aditional cost: Indirect Manpower and Equipments.
Date
2022.
Location
SAUDI ARABIA.
Service
Extension of Time Evaluation (Analysis Forensic of the Schedule), Quamtum of Additional Cost.
Final Value of the Project
USD 21.741.713,56
Project Type
TEMPORARY FACILITIES – GAS PLANT
Project Description
TEMPORARY FACILITIES CONSTRUCTION
Project Scope
Temporary Camp for 500 Persons, Temporary Offices and Site Warehouse.
Our Services
Forensic Schedule Analysis. Evaluation of the Extension of Time (EoT), responsabilities and Quantum: Indirect Manpower and Equipments and Productivity Loss in Direct Manpower.
Date
2009.
Location
SAUDI ARABIA.
Service
Major Impacts on Project Costs
Final Value of the Project
USD 480.000.000
Project Type
GAS PLANT
Project Description
Increase 851 MMSCFD in gas processing capacity
Project Scope
Gas inlet handling facilities, one Sour Water Stripper Unit, two DGA gas treating units, one Sulfur Recovery Unit with thermal oxidizer, one TEG/propane refrigeration system for gas Dehydration and Dewpoint Control, two Sales Gas Compressors, and the re-gearing of the four existing Sales Gas Compressors.
Our Services
Extension of Time analysis due to several Change Orders Request, Quantum of Indirect Personnel, Subcontractors.
Date
2002.
Location
VENEZUELA.
Service
Claim based on pending Aditional Works
Final Value of the Project
USD 3.000.000
Project Type
GAS COMPRESSOR PLAN.
Project Description
Electrical and Instrumentation Works
Project Scope
Electrical and Instrumentation Works
Our Services
Extension of Time due to Material Delay Delivery, and Quantum for Manpower and Equipments additional Costs.
Date
2001.
Location
VENEZUELA.
Service
Extension of Time due to Material Delay Delivery, and Quantum for Manpower and Equipments additional Costs.
Final Value of the Project
USD 600.000
Project Type
Small Bore Piping Installation
Project Description
Installation of 6.000 LM of Small Bore Pipe, includind Pipe Support prefabrication and insallation.
Project Scope
Pipe for Services: Water, Air, Vapor and Nitrogen. Cooling Water Systems, Fire Water Systems and Drinking Water.
Our Services
Extension of Time due to Material Delay Delivery, and Quantum for Manpower and Equipments additional Costs.
Date
1999
Location
VENEZUELA.
Service
Extension of Time due to Material Delay Delivery, and Quantum for Manpower and Equipments additional Costs.
Final Value of the Project
USD 3.200.000
Project Type
CIVIL WORKS – GAS PLANT
Project Description
Erection Precast Concrete Pipe Rack.
Project Scope
Erection Precast Concrete Pipe Rack. 358 Columns and 991 Beams, with a total Weigth: 7,791 Tons.
Our Services
Extension of Time due to delays in the delivery of Materials, calculation of the Impacts on the cost of Direct and Indirect Personnel, and Equipment.
Date
1998
Location
VENEZUELA.
Service
CLAIM PENDING ADDITONAL WORKS
Final Value of the Project
USD 13.200.000
Project Type
GAS COMPRESSOR PLANT
Project Description
Erection of two (2) Gas TurboCompressors
Project Scope
Erection of two (2) Gas TurboCompressors, KOD and Flare, including all the Pipe Prefabrication and Intalations, Electricity and Instrumentation Works.
Our Services
Support and negotiate several Change Orders pending.
Date
1992.
Location
VENEZUELA.
Service
Negotiate additional works, quantities increase, and over cost.
Final Value of the Project
USD 7.000.000
Project Type
GAS COMPRESSOR PLANT
Project Description
Erection of three (3) Gas Compressors Miniplants
Project Scope
Erection of three (3) Gas Compressors Miniplants with Electrical Motor of 10.000 HP, including Modular Control and Power Room. Prefabrication and instalation of Pipe. Electrical and Instrumentation works
Our Services
Contract close, including additional work, quantities increase, and claim for overcosts.